Project title
AL-Busdaira water pip
Beneficiary side
Fallujah rehabilitation committee
Contract no.
4-06-01-1029
Location
Iraq-Anbar-Fallujah-AL-Busdaira district
Contract amount
160,000 $
Contract period
12/6/2004-15/8/2005
Description
This reason of this project is to supply AL-Busdaira area with clean water the total pipe line was 3500 M.L with 6 in D, the excavation work was 3500 M.L with 1 M depth and also to cover the pipe with clean river sand before burying it to the ground level and also the work include making main halls with valves for maintenance , we made a weekly report along the project time with photos for each step of the work and when the work was completed the people of AL-Busdiara area were happy because the clean water arrived to there houses which was a dream in the past period
اسم المشروع
شبكة الماء الصافي في ابوسديرة
الجهه المستفيده
لجنه اعمار الفلوجه
رقم المشروع
4-06-01-1029
موقع المشروع
الانبار / الفلوجة / منطقه ابو سديرة
مبلغ العقد
$ 160,00
مده المشروع
12/6/2004-15/8/ 2005
التفاصيل
الغرض من هذا المشروع هو تجهيز منطقة البوسديرة بالماء الصافي للشرب ، طول الانبوب المجهز والمنفذ هو 3500 م . ط بقطر 6 انج ، الحفريات كانت بطول 3500 م . ط بعمق 1م وكان العمل يتضمن تغطية الانبوب بالرمل النهري قبل اعادة الاملاء الى مستوى الارض الطبيعية وتجهيز وربط اقفال السيطرة على الشبكة مع عمل المانهولات الخاصة بها . لقد قمنا بعمل تقارير اسبوعية طيلة مدة المشروع وعند انتهاء المشروع تم ايصال الماء الصافي الى منطقة ابو سديرة.