AL-REHYAD SCHOOL RENOVATION

Project title

AL-Rehyad school renovation

Beneficiary side

Fallujah rehabilitation committee

Contract no.

4-05-03-1020

Location

Iraq-Anbar-Fallujah-Saqlawya

Contract amount

36,547 $

Contract period

10/6/2004-10/8/2004

AL-Rehyad school in AL-Saqlawya area served about 500 students from boys and girls but there was no facilities in this school to serve the students. when the contract was awarded we tried hard to renovate this school to make it workable for the students so we done every thing such us( plastering , painting inside and out side , casting the out side yards and walkways , fixing the floors for classes , electricity , new furniture for teachers , doors , windows, roofing , out side green area , etc... ) we tried to make the work quality on top because it is far a way from cities and it was a warded before but the contractor( the last contractor )says that no body will inspect his work and it is a very black point in the profile of any contractor thinking like that . when the school was completed we deliver it and it was more than workable and we think this is important more than money


اسم المشروع

مشروع اعادة ترميم مدرسة الرياض الابتدائية

الجهه المستفيده

لجنه اعمار الفلوجه

رقم المشروع

4-05-03-1020

موقع المشروع

الانبار / الفلوجة / الصقلاوية

مبلغ العقد

36,547 $

مده المشروع

10/6/2004-10/8/2004

التفاصيل

مدرسة الرياض الابتدائية في الصقلاوية تخدم خمسمائة طالب تقريبا من كلا الجنسين ، كانت هذه المدرسة اسوء حالاتها وذلك بسبب تردي الخدمات في تلك المنطقة وعندما تم احالة هذا المشروع لشركتنا قمنا بترميم هذه المدرسة بجميع فقراتها ( اعمال البياض ، الصبغ الداخلي والخارجي ، صب الساحات الخارجية والمماشي ، تطبيق الكاشي الموزاييك للصفوف ، اعمال الكهرباء ، تجهيز اثاث جديد للمدرسين ، تجهيز ونصب ابواب جديده ، تجهيز ونصب شبابيك جديده ، اعمال التسطيح ، اعمال الساحات الخضراء الخارجية ، الخ ) وقمنا بانهاء العمل حسب المواصفات الفنية وبجوده عالية وضمن المدة المقررة للمشروع .