ABU SDIRA WATER PIPE

Project title

AL-Busdaira water pip

Beneficiary side

Fallujah rehabilitation committee

Contract no.

4-06-01-1029

Location

Iraq-Anbar-Fallujah-AL-Busdaira district

Contract amount

160,000 $

Contract period

12/6/2004-15/8/2005

Description

This reason of this project is to supply AL-Busdaira area with clean water the total pipe line was 3500 M.L with 6 in D, the excavation work was 3500 M.L with 1 M depth and also to cover the pipe with clean river sand before burying it to the ground level and also the work include making main halls with valves for maintenance , we made a weekly report along the project time with photos for each step of the work and when the work was completed the people of AL-Busdiara area were happy because the clean water arrived to there houses which was a dream in the past period



اسم المشروع

شبكة الماء الصافي في ابوسديرة

الجهه المستفيده

لجنه اعمار الفلوجه

رقم المشروع

4-06-01-1029

موقع المشروع

الانبار / الفلوجة / منطقه ابو سديرة

مبلغ العقد

$ 160,00

مده المشروع

12/6/2004-15/8/ 2005

التفاصيل

الغرض من هذا المشروع هو تجهيز منطقة البوسديرة بالماء الصافي للشرب ، طول الانبوب المجهز والمنفذ هو 3500 م . ط بقطر 6 انج ، الحفريات كانت بطول 3500 م . ط بعمق 1م وكان العمل يتضمن تغطية الانبوب بالرمل النهري قبل اعادة الاملاء الى مستوى الارض الطبيعية وتجهيز وربط اقفال السيطرة على الشبكة مع عمل المانهولات الخاصة بها . لقد قمنا بعمل تقارير اسبوعية طيلة مدة المشروع وعند انتهاء المشروع تم ايصال الماء الصافي الى منطقة ابو سديرة.